Exits 132 kv CP Strettoia
HIGH VOLTAGE

Exits 132 kv CP Strettoia

Scope

Variations to the 132 kv lines n.500, 550 and 565 of the main passageway in Strettoia.

Commissioned by

Terna Rete Italia spa

Budget

565,765 €

Location

Lucca

Year

2019