Installation of catenary conductors and switches on the Pragersko-Hodos line in Slovenia
ELECTRIC TRACTION

Installation of catenary conductors and switches on the Pragersko-Hodos line in Slovenia

Scope

Installation of catenary conductors and switches on the Pragersko-Hodos line. The electrification of the Pragersko-Hodos section on behalf of the Slovenian Ministry of Infrastructures was successfully carried out with a 440 sq. mm. contact line and the installation of switch-disconnectors with 25 kV insulation.

Commissioned by

Republic of Slovenia Ministry of Infrastructure

  • Supply and assembly of the contact line with the assembly of the accessories on the new supports, the installation of all the moorings of the contact line both fixed and regulated, the laying of all the suspensions with 25kV isolation on the contact line, the laying of all the 440 sq. mm. conductors on the rails; the laying of all the conductors on the secondary rails; the installation of the grounding system;
  • Installation of all the disconnectors; the motorization and control of all the 3 KV disconnectors and all the necessary connections; supply and assembly of low voltage systems in the stations and section stops;
  • Supply and assembly of fiber-optic cable for derivation and connection to the ESS;
  • Supply and assembly of cable ducts; supply of spare parts;